August 10, 2017
SEM 02 AUGUST/2017
JOBS: BEFORE BOAT LAUNCH (07th. – 09th.)
-
DETAILS JOBS CONTINUES ON SUN DECK.
-
MARBLE ON BARBECURE BAR WAS INSTALLED.
-
ELEVATOR JOBS CONTINUES AND INSTALLING STAINLESS STEEL WALLS.
-
AFT UPPER DECK LAMP WAS INSTALLED.
-
GENERAL PREPARATIONS ARE MADE BEFORE BOAT LAUNCH.
-
BOTH ANCHORS WERE INSTALLED.
-
PROPELLER NUTS PROTECTION WERE INSTALLED.
-
BOTH BOW THRUSTER PROPELLER WERE INSTALLED.
-
BOTH STABILAZER BLADES WERE INSTALLED.
AFTER BOAT LAUNCH (09th. – 11th.)
-
ON SUN DECK ANTTENNA STRUCTURE WAS INSTALLED.
-
ON CREW CABINS CONTINUE WITH CARPENTRY JOBS.
-
ON CREW MESS CONTINUE WTH CARPENTRY JOBS.
-
WAS RECEIVED MARINE GAS OIL. (14,000 LTS.)
-
A/C SYSTEM TESTS ARE STARTED.
August 03, 2017
SEM 01 AUGUST/2017
JOBS DONE,
-
ON SUN DECK, CONTINUED WITH POLISH AND REPAIR DETAILS OF PAINT ON SUN DECK (BAR TABLE, BARBECUE TABLE, STAINLESS STEEL TABLE, DOORS AND ACCESSORIES).
-
ON SUN DECK, STAINLESS STEEL TABLE GLASS WAS RECEIVED.
-
ON SUN DECK, FIXING SB BAR.
-
CARPENTRY JOBS CONTINUED IN THE SKY SALON (UPPER DECK).
-
CONTINUE WITH CARPENTRY JOBS IN UPPER DECK LOBBY.
-
CARPENTRY JOBS AND WIRES CONNECTION CONTINUE ON PILOT HOUSE.
-
CONTINUE WITH INSTALLATION OF PUMPS AND PVC PIPES ON JACUZZI.
-
REGTANGULAR TEAK TABLE WITH MARBLE WERE RECEIVED, FOR UPPER DECK.
-
MARBLE IN STAINLESS STEEL UPPER DECK TABLE WAS INSTALLED.
-
CONTINUE WITH REPAINT AND FIX DETAILS ON AFT DECK.
-
MAIN SALON LAMP WAS RECEIVED AND INSTALLED.
-
CONTINUE WITH INSTALLATION OF TV AND AUDIO RACK, ON THE GALLEY.
-
CONTINUE WITH CARPENTRY JOBS ON MAIN DECK SB LOBBY.
-
CONTINUE INSTALLING FLOOR ON MAIN DECK PS LOBBY.
-
STAR TO INSTALLING STAINLESS STEEL WALLS ON ELEVATOR..
-
CONTINUE WITH CARPENTRY JOBS IN VIP LOBBY.( LOWER DECK)
-
ALL EMERGENCY STEEL WINDOWS WERE STORED UNDER VIP CABINS BETHS.
-
CONTINED INSTALLING MARBLE FOOR ON VIP CABINS BATHROOMS.
-
CONTINUE WITH CARPENTRY JOBS IN CREW CABINS
-
CONTINUE WITH CARPENTRY JOBS IN CREW MESSROOM
-
INSULLATION UNDER CREW MESS SEAT WAS INSTALLED.
-
CONTINUE WTH CARPENTRY JOBS ON STAIRS TO CREW DECK.
-
MAIN ENGINE COOLANT DEPOSITS WERE INSTALLED, WERE CHANGE POSITION.
-
CONTINUED WITH WATER MAKER INSTALLATION.
-
BOTH SIDES SHAFT SEAL PROTECTIONS PLATES WERE INSTALLED.
-
CHIANS AND ANCHORES WERE RECEIVED.
-
THE WHOLE SCAFFOLDING WAS REMOVED ARROUND THE BOAT, EXCEPT FOR STERN.
July 27, 2017
SEM 04 JULY//2017
JOBS DONE,
-
CONTINUED WITH POLISH AND REPAIR DETAILS OF PAINT ON SUN DECK (BAR TABLE, BARBECUE TABLE, DOORS AND ACCESSORIES).
-
SUN DECK, CONTINUE WITH DETAILS ON TEAK DECK.
-
SUN DECK, THE STAINLESS STEEL TABLE AND THE TEMPERED GLASS OF LATERAL BARS (PS AND SB) WERE RECEIVED.
-
UPPER DECK, FRIGOBAR AND ICE MAKER WERE RECEIVED AND INSTALLED.
-
UPPER DECK, CARPENTRY JOBS CONTINUED IN THE SKY SALON,START TO INSTALL ROOF CELING AND TESTING LIGHTS.
-
UPPER DECK, IT FINISHED INSTALLING FLOOR IN SKY SALON.
-
UPPER DECK, START CARPENTRY JOBS IN LOBBY.
-
CARPENTRY JOBS CONTINUE ON PILOT HOUSE.
-
CONTINUE WITH INSTALLATION OF PUMPS AND PVC PIPES ON JACUZZI.
-
BOTH SIDES MR LOUI NAMES WERE MOUNTED.
-
MAIN DECK, CONTINUE WITH REPAINT AND FIX DETAILS ON AFT DECK.
-
CONTINUE WITH INSTALLATION OF TV AND AUDIO RACK, ON THE GALLEY.
-
MAIN DECK, START CARPENTRY JOBS ON SB LOBBY.
-
THE AFT MR LOUI NAME WAS MOUNTED..
-
LOWER DECK, CONTINUE WITH CARPENTRY JOBS IN VIP LOBBY.
-
LOWER DECK, ALL EMERGENCY STEEL WINDOWS WERE INSTALLED.
-
LOWER DECK/CREW CABINS, CONTINUE WITH CARPENTRY JOBS.
-
LOWER DECK/CREW MESS, CONTINUE WITH CARPENTRY JOBS. THE DIMENTIONS OF THE SEAT WERE FIX IT.
-
CONTINUE WTH CARPENTRY JOBS ON STAIRS TO CREW DECK.
-
ENGINE ROOM, CONTINUE TO INSTALLING ROOF CELING.
-
ENGINER ROOM, ALL LED LIGHTS WERE INSTALLED.
-
MAIN ENGINE COOLANT DEPOSITS WERE INSTALLED.
-
3000 LTS. OF MARINE GAS OIL WAS RECEIVED.
-
BOTH SIDES SHAFT SEAL PROTECTIONS PLATES, WERE RECEIVED AND PAINTED.
-
ALL ZINC ANODES WERE INSTALLED ON HULL BOTTOM.
-
ALL HULL BOTTOM WAS PAINTED.
July 20, 2017
SEM 03 JULY//2017
JOBS DONE,
-
SUN DECK, CONTINUED WITH POLISH AND REPAIR DETAILS OF PAINT ON SUN DECK, INSTALLING BAR TABLE, BARBECUE TABLE, DOORS AND ACCESORIES.
-
INSTALLATION OF ELECTRIC PISTONS FOR ELEVATOR DOOR, ON SUN DECK
-
CONTINUE WITH DETAILS OF TEAK ON SUN DECK.
-
CONTINUE WITH CARPENTRY JOBS IN SKY SALON. ON UPPER DECK.
-
CONTINUE WITH DETAILS OF TEAK ON UPPER DECK.
-
CONTINUE INSTALLING WOOD FORNITURES OF PILOT HOUSE EQUIPMENT.
-
START TO INSTALL JACUZZI PUMPS.
-
CONTINUE WITH REPAINT AND FIX DETAILS ON ARROUND ALL AFT DECK.
-
FINISHED TO INSTALL FLOOR, ON MAIN SALON.
-
START TO INSTALL PIECES OF MARBLE ON MAIN SALON.
-
START TO INSTALL TV AND AUDIO RACK, ON THE GALLEY.
-
START CARPENTRY JOBS ON VIP LOBBY, IN LOWER DECK.
-
CONTINUE JOBS IN BATHROOMS, INSTALLING MARBLE AND GLASS DOORS. ON VIP CABINS.
-
CONTINUE WITH CARPENTRY JOBS, ON CREW MESS.
-
START CARPENTRY JOBS ON STAIRS TO CREW DECK.
-
START TO INSTALL GAUGES AND 8 MM. PIPING OF ALL PUMPS, IN ENGINE ROOM.
-
CONTINUE TO INSTALLING ROOF CELING IN ENGINE ROOM
-
START TO MANUFACTURED OF SHAFT SEAL PROTECTIONS, ON BOTH SIDES.
July 13, 2017
SEM 02 JULY//2017
JOBS DONE,
-
CONTINUED WITH POLISH AND REPAIR DETAILS OF PAINT ON SUN DECK, INSTALLING DOORS AND ACCESORIES.
-
IN SUN DECK, WAS INSTALLED LIGHTS, CONNECTED AND TESTED.
-
START TO INSTALL ELEVATOR DOOR, IN SUN DECK
-
WAS INSTALLED STAIR HANDRAILS FROM UD TO SD.
-
CONTINUE WITH CARPENTRY JOBS ON UPPER DECK SALON.
-
WAS INSTALLING ROOF CELING ON CAPTAIN CABIN.
-
START TO INSTALL WOOD FORNITURES OF PILOT HOUSE EQUIPMENT.
-
WAS MOUNTED ROOF CELING ON AFT DECK OF UPPER DECK.
-
WAS INSTALLED LIGHTS AND WAS TESTED IN AFT DECK OF UPPER DECK.
-
BOW TEAK WAS DETAILED.
-
CONTINUE TO INSTALL FLOOR, ON MAIN SALON.
-
IN THE GALLEY WAS INSTALLED THE MARBLE.
-
IN MASTER CABIN, WAS FINISHED TO INSTALL FLOOR.
-
IN MAIN DECK BATHROOM WAS MOUNTED MARBLE FLOOR.
-
WAS MOUNTED ROOF CELING ON AFT DECK OF MAIN DECK
-
WAS INSTALLED LIGHTS AND WAS TESTED ON AFT DECK OF MAIN DECK.
-
WAS INTALLED STAIR HANDRAILS FROM MD TO UD.
-
CONTINUE WITH CARPENTRY JOBS ON CREW MESS AND CREW CABINS.
-
START TO INSTALL TENDER SUPPORT IN THE GARAGE.
-
WAS MOUNTED TEAK ON GARAGE DOOR.
-
CONTINUE WITH CONNECTION OF WIRES AND CABLES ON ELECTRIC PANELS IN ENGINEROOM.
-
SOUND ALARMS (FIRE, GENERAL AND FIRE) WAS INSTALLED.
-
CONTINUE INSTALLING ROOF CELING IN ENGINE ROOM.
-
CONTINUE WITH INSTALLATION OF WATER MAKER.
-
WAS SUPPLY LUB OIL AND COOLANT AT MAIN ENGINES AND LUB OIL AT GEAR BOXES.
July 06, 2017
SEM 01 JULY//2017
JOBS DONE,
-
ON SUN DECK CONTINUED WITH POLISH AND REPAIR DETAILS OF PAINT ON SUN DECK, INSTALLING DOORS AND ACCESORIES.
-
CONTINUE TO INSTALL TEAK STAIRS FROM UPPER DECK TO SUN DECK.
-
CONTINUE WITH CARPENTRY JOBS ON SKY SALON ON UPPER DECK.
-
WAS FINISHED CARPENTRY JOBS ON CAPTAIN CABIN.
-
CONTINUED INSTALLING TEAK STEPS ON BOW DECK.
-
WAS MOUNTED MAIN PORTABLE PASARELLA OUT SIDE SB PILOT HOUSE DOOR.
-
CONTINUE TO INSTALL FLOOR, ROOF CELING AND TESTED LIGHTS ON MAIN SALON.
-
IN GALLEY WAS INSTALLED FLOOR, START TO INSTALL ROOF CELING AND TESTED OF LIGHTS.
-
IN MASTER CABIN START TO INSTALL FLOOR.
-
CONTINUE WITH INTERIOR STEPS FROM MAIN DECK TO UPPER DECK.
-
CONTINUE WITH INTERIOR STEPS FROM MAIN DECK TO LOWER DECK.
-
START TO CARPENTRY JOBS ON ELEVATOR.
-
WAS INSTALLED ANCHOR WINCHS..
-
IN GUEST AND TWIN CABINS CONTINUED WITH INSTALLATION OF MARMOL ON BATHROOMS, ALSO WAS INSTALLED SHOWER MIXERS.
-
IN CREW MESS WITH CARPENTRY JOBS ON CREW MESS.
-
ON GARAGE WAS INSTALLED ROOF CELING AND TESTED LIGHTS.
-
IN ENGINE ROOM CONTINUED WITH CONNETING WIRES AND CABLES ON ELECTRIC PANELS.
-
IN ENGINE ROOM START TO MOUNTED OF STAINLESS STEEL DIAMOND PLATES.
-
IN ENGINE ROOM CONTINUED OF INSTALLATION OF ROOF CELING.
-
IN ENGINE ROOM START TO INSTALL LIGHTS AND TESTED.
-
IN ENGINE ROOM WAS INSTALLED FM200 BOTTLES.
-
START TO INSTALLATION OF WATER MAKER.
-
WAS INSTALLED STRUCTURE FOR ENGINE EXHAUST GASES, UNDER HULL.
-
WAS INSTALLED STABILIZER BLEDES.
June 29, 2017
SEM 05 JUNE/2017
JOBS DONE,
-
CONTINUED WITH POLISH AND REPAIR DETAILS OF PAINT ON SUPERIOR AND INFERIOR STRUCTURE ON SUN DECK AND INSTALL DOORS AND ACCESORIES.
-
WAS INSTALLED SUNROOF.
-
WAS INSTALLED TEMPERED GLASS, ON SUN DECK
-
CONTINUED JOBS OF MANUFACTURED OF STAIRS HANDLES FROM UD TO SD.
-
START CARPENTRY JOBS ON SALON IN UPPER DECK
-
CONTINUED OF CARPENTRY JOBS ON CAPITAN CABIN.
-
WAS RECEIVED STAIRS HANDLES FROM MD TO UD, READY TO INSTALL.
-
CONTINUE WITH INSTALLATION OF TEAK STEPS ON AFT STAIRS TO UD.
-
CONTINUED TO INSTALL FLOOR ON MAIN SALON.
-
IN GALLEY WAS STARTED TO INSTALL FLOOR.
-
MASTER CABIN CONTINUE WITH TOUCH UP AND REPAIR DETAILS.
-
START WITH INTERIOR STEPS ON MAIN DECK TO UPPER DECK.
-
START WITH INTERIOR STEPS ON MAIN DECK TO LOWER DECK.
-
IN GUEST AND TWIN CABINS CONTINUED TO INSTALL MARMOL ON BATHROOMS.
-
CONTINUE CARPENTRY JOBS ON CREW CABINS
-
START CARPENTRY JOBS ON CREW MESS.
-
WAS INSTALLED WASHER AND DRIER MACHINE ON CREW MESS AND ENGINEER CABIN.
-
IN GARAGE WAS PAINTED INSIDE THE BILGES.
-
IN ENGINE ROOM CONTINUED WITH CONNETING WIRES AND CABLES ON ELECTRIC PANELS.
-
SHORE LINE WAS CONNECTED TO MAKE TEST FOR DIFFERENTS EQUIPMENTS AS HYD. SYST. FOR GARAGE DOOR, AFT PASSARELA, FANS COILS ARROUND MAIN DECK AND LOWER DECK, (MAIN SALON, MASTER CABIN, GUEST AND TWIN CABIN ARE WORKING ONLY BLOWERS)
-
START TO MOUNTED TOP PLATES IN ENGINE ROOM.
-
WAS INSTALLED GENERATORS FUEL OIL FILTERS.
-
WAS RECEIVED DIAMON PLATES.
-
START TO INSTALL STRUCTURE FOR ENGINES EXHAUST GAS, UNDER HULL
-
WAS INSTALLED ANCHOR CHAIN DUCTS.
June 22, 2017
SEM 04 JUNE/2017
JOBS DONE,
-
IN SUN DECK, START OF POLISH AND REPAIR DETAILS OF PAINT ON SUPERIOR AND INFERIOR STRUCTURE ON SUN DECK AND INSTALL DOORS AND ACCESORIES.
-
WAS PAINT TOP STRUCTURE ON AFT UPPER DECK.
-
CONTINUED JOBS ON INSTALLATION OF STAIRS HANDLES FROM UPPER DECK TO SUN DECK.
-
CONTINUE CARPENTRY JOBS ON SALON ON UPPER DECK.
-
CONTINUED OF CARPENTRY JOBS ON CAPITAN CABIN AND INSTALLED FAN COIL.
-
WAS FINISHED WITH STAIRS HANDLES FROM MAIN DECK TO UPPER DECK, AND SENT TO POLISH AND DETAILED.
-
CONTINUED TO INSTALLING TEAK STEPS.
-
START TO INSTALL FLOOR ON MAIN SALON.
-
WAS INSTALLED APPLIANCES IN MAIN SALON (ICE MAKER, FRIGOBAR AND WINE COOLER)
-
SALON ROOM AND GALLEY, THE TOP COVERS WAS REMOVED AND SEND TO PAINT.
-
IN GALLEY WAS MOUNTED KITCHED ISLAND.
-
MASTER CABIN WAS FINISHED WITH CARPENTRY JOBS AND START TO TOUCH UP AND REPAIR DETAILS..
-
IN GUEST CABINS START AND FINISHED TO TOUCH UP PAINT AND REPAIR DETAILS.
-
IN TWIN CABINS START TO TOUCH UP PAINT AND REPAIR DETAILS AND START TO MOUNT MARMOL ON BATHROOMS.
-
IN CREW CABINS, CONTINUE CARPENTRY JOBS AND INSTALLED CLOSETS.
-
PREPAIR TO PAINT ARROUND SEAL OF GAREGE DOOR.
-
IN ENGINE ROOM, CONTINUED WITH CONNETING WIRES AND CABLES ON ELECTRIC PANEL AND INSTALLED BATT BANKS OF GENERATORS.
-
IN ENGINER ROOM, WAS MOUNTED STRUCTURES OF PLATES SUPPORTS.
-
IN HULL, START TO INSTALL STRUCTURE FOR EXHAUST GASES OUTLET OF DIESEL ENGINES.
-
WAS INSTALLED ELECTRIC MOTORS FOR ANCHOR WINCHS AND CAPSTANS
June 15, 2017
SEM 03 JUNE/2017
JOBS DONE,
-
WAS PAINTED ON INFERIOR STRUCTURE ON SUN DECK.
-
WAS FIXED TOP STRUCTURE ON AFT UPPER DECK, CORRECTION OF PROPERLY LEVELING, SUGGESTED BY SURVEYOR JUAN.
-
CARPENTRY JOBS ON SALON AND BATHROOM
-
PILOT HOUSE, CONTINUE CONNECTED WIRES AND CABLES ON ELECTRIC PANELS.
-
CONTINUED OF CARPENTRY JOBS ON CAPITAN CABIN.
-
WAS PAINTED ON BOW DECK.
-
CONTINUE INSTALLING TEAK ON JACUZZI AND STEPS.
-
AFT DECK, CONTINUED JOBS ON INSTALLATION OF STAIRS HANDLES.
-
CONTINUED CARPENTRY JOBS IN SALON ROOM, GALLEY AND MASTER CABIN ON TOP COVERS.
-
WAS FINISHED WITH CARPENTRY JOS, WAS MOUNTED DITAILS, TV´S AND TESTED LIGHTS.
-
WAS FINISHED WITH CARPENTRY JOS, WAS MOUNTED DITAILS AND TESTED LIGHTS.
-
CONTINUE CARPENTRY JOBS AND INSTALLED OF FAN COILS.
-
IN GARAGE DOOR, CONTINUED WITH CARPENTRY JOBS AND DETAILS JOBS ON GAREGE SEAL DOOR.
-
ENGINE ROOM, CONTINUED WITH INSTALLATION OF ELECTRICAL PANELS, CONNETING WIRES AND CABLES.
-
ENGINER ROOM, COUNTINUED MOUNTED STRUCTURES OF SUPPORTS PLATES.
-
WAS POLISH AND APPLIED PROTECTIVE PAINT AT PROPELLERS AND RUDDERS.
June 08, 2017
SEM 02 JUNE/2017
JOBS DONE,
-
WAS PAINT ANTTENA STRUCTURE AND PREPARATION INFERIOR STRUCTURE ON SUN DECK.
-
CARPINTER JOBS ON UPPER, MAIN AND LOWER DECK.
-
CONTINUED WITH INSTALLATION OF ELECTRICAL BOXES.
-
WAS INSTALLED HYD. PISTONS FOR GARAGE DOOR.
-
ENGINE ROOM. WAS ELECTRICAL PANEL.
-
GALLEY WAS INSTALLED MAIN OVEN, MICROWAVE AND DISHWASHER MACHINE.
-
CONTINUED JOBS ON ELEVATOR.
-
WAS MOUNTED BATTERIES ON BATTERY BANKS.
-
INSTALLED STRUCTURE SUPPORTS FOR PLATES IN ENGINE ROOM
June 01, 2017
SEM 01 JUNE/2017
JOBS DONE,
-
WAS PAINT ANTTENA STRUCTURE ON SUN DECK.
-
CARPINTER JOBS ON UPPER, MAIN AND LOWER DECK.
-
CONTINUED WITH INSTALLATION OF FAN COOLERS ON UPPER, MAIN AND LOWER DECKS.
-
WAS INSTALLED GARAGE DOOR.
-
ENGINE ROOM. WAS INSTALLED FAN COIL IN ATF PS SPACE, WAS INSTALLED HYD PISTONS FOR GAREGE DOOR.
-
GALLEY WAS COSTUMER REFRIGERATOR AND FREZZER.
-
WAS INSTALLED ELEVATOR GLASS DOOR, ON MAIN DECK AND UPPER DECK.
May 24, 2017
SEM 04 MAY/2017
JOBS DO IT,
-
PREPARE TO PAINT ANTTENA STRUCTURE ON SUN DECK.
-
CARPINTER JOBS ON UPPER, MAIN AND LOWER DECK.
-
ENGINE ROOM, REMOVE SMALL WATER MAKER, INSTALL PIPES OF AIR COMPRESSOR SYSTEM, INSTALL HYD. BLOCK VALVES FOR GARAGE DOOR ON LOWER DECK. INSTALL COOLER FAN ON PS AFT SPACE. INSTALL FLANGES FOR COUPLING BETWEEN SHAFT PROPELLER AND GEAR BOXES.